AUT WE Stage 1 – School of Art & Design

  • Division: Interiors
  • Location: Auckland
  • Started: August 2007
  • Cost: $3.6 million
  • Client: AUT University
  • Completed: February 2008

Two levels of demolition and fit-out along with a fire system upgrade to the entire building, all completed within a tight timeframe.

Staged commencement dates for both levels were required, with level 4 being allocated only 11 weeks over the Christmas period from the commencement of demolition through to handover for AUT fit-out items.

Specialised offshore materials were required and non-standard items were also sourced from within New Zealand. Features include: patterned punched aluminium ceiling panels, combined with Aluart anodised aluminium panels at the entrance of the building as well as classrooms; natural random timber providing for breakout areas between classrooms and feature walls within; ceiling bulkheads and detailing giving the effect of floating ceilings; and aluminium panelled walls and canopy at the entrance, along with a glazed shop-front for displays, and glazed balustrade.

Other Parties

  • Name: RTA Studio
  • Role: Architect & Project Manager

More <>

Current and Recent Projects

Building
Laminex Distribution Centre >> The new Laminex Distribution Centre is rapidly taking shape. 
Engineering
Victoria Park Alliance >> A Fletcher , Higgins, Beca, Parsons & Brinckerhoff and NZ Transport Agency alliance to design and construct a 2.2km upgrade of SH1 between Wellington Street and the Auckland harbour bridge.
Interiors
AUT WE Stage 2 – School of Art & Design >> The second stage of AUT’s School of Art & Design refurbishment to Levels 5-7 (the two-level first stage refurbishment was completed a year ago).
South Pacific
Leadership Code Commission and Ombudsman’s Office >> Refurbishment of existing and additional offices and amenities.