Avalon Drive Bypass

  • Division: Engineering
  • Location: Hamilton
  • Started: February 2007
  • Cost: $26.6 million
  • Client: Transit NZ
  • Completed: October 2008

Construction of two major roundabouts, two bridges, and a 2.7km two-lane bypass off Avalon Drive.

The project provided a free-flowing, high-capacity route bypassing a congested section of Avalon Drive from Rotokauri Road to Forest Lake Road.


One of the main challenges was the construction of the Norton Road rail over-bridge with its numerous service diversions, signalling shifts and work running alongside the Main Trunk rail line – one of the busiest rail track lines in the Waikato.


Articles

Safely Does It
The Brian Perry Civil team at the Avalon Drive Bypass project in Hamilton started the year on a positive note, racking up 12 months with zero LTIs (Lost Time Injuries).

Other Parties

  • Name: Higgins
  • Role: Civil Contractor
  • Name: Schick Construction
  • Role: Earthworks

More <>

Current and Recent Projects

Building
Laminex Distribution Centre >> The new Laminex Distribution Centre is rapidly taking shape. 
Engineering
Victoria Park Alliance >> A Fletcher , Higgins, Beca, Parsons & Brinckerhoff and NZ Transport Agency alliance to design and construct a 2.2km upgrade of SH1 between Wellington Street and the Auckland harbour bridge.
Interiors
AUT WE Stage 2 – School of Art & Design >> The second stage of AUT’s School of Art & Design refurbishment to Levels 5-7 (the two-level first stage refurbishment was completed a year ago).
South Pacific
Leadership Code Commission and Ombudsman’s Office >> Refurbishment of existing and additional offices and amenities.