MacKay’s to Waikanae Preload

  • Division: Engineering
  • Location: Wellington
  • Started: December 2008
  • Cost: $8.7 million
  • Client: ONTRACK
  • Completed: Under Construction

Brian Perry Civil is helping to make commuting on the rail line between Waikanae and Wellington easier and quicker.

The main project, for which the new MacKay’s to Waikanae Preload contract is preparation, is to construct a second rail track adjacent to the existing North Island Main Trunk. This will run for 15km between Paekakariki and Waikanae, north of Wellington.


The contract involves the preloading of swamp areas to accelerate the settlement of organic soils in advance of the main earthworks contract.


Much of the project involves working in a narrow corridor between the rail line and SH1 which offers challenges in terms of safety and programming.

Articles

Peat in the swamp
Brian Perry Civil is helping to make commuting on the ONTRACK rail line between Waikanae and Wellington easier and quicker.

Other Parties

  • Name: Opus
  • Role: Engineer

More <>

Project Facts

  • 100 trains and 30,000 vehicles per day through site

  • 100,000m3 earthworks

  • 85,000m2 of geotextiles and geogrids

  • 120,000m wick drains (prefabricated vertical drains)

Current and Recent Projects

Building
Laminex Distribution Centre >> The new Laminex Distribution Centre is rapidly taking shape. 
Engineering
Victoria Park Alliance >> A Fletcher , Higgins, Beca, Parsons & Brinckerhoff and NZ Transport Agency alliance to design and construct a 2.2km upgrade of SH1 between Wellington Street and the Auckland harbour bridge.
Interiors
AUT WE Stage 2 – School of Art & Design >> The second stage of AUT’s School of Art & Design refurbishment to Levels 5-7 (the two-level first stage refurbishment was completed a year ago).
South Pacific
Leadership Code Commission and Ombudsman’s Office >> Refurbishment of existing and additional offices and amenities.