PRINT

Tuai Penstock Foundations

  • Division: Engineering
  • Location: Waikato
  • Started: February 2009
  • Cost: $1.2 million
  • Client: Genesis Energy
  • Completed: June 2009

The project provided new foundations for the penstocks – large enclosed intake pipes – that take water from Lake Whakamarino down to Genesis Energy’s Tuai Powerhouse.

The job involved 16 bored piles and eight substantial reinforced concrete beams that run under the penstocks as well as longitudinal concrete beams linking the piles either side of the penstocks. Once the beams were completed, pedestals were constructed on top of the beams to support the penstocks.


The project had a challenging site location: a very steep slope immediately adjacent to the penstocks. The penstocks were in constant use, carrying extremely high water pressures. Operating plant, especially the Lo-Drill, so close to the them meant a high degree of risk had to be mitigated.

Articles

High pressure work, but the piles were bored
Brian Perry Civil achieved great things on a difficult site for this $1.2 million infrastructure project.

More <>

Current and Recent Projects

Building
Laminex Distribution Centre >> The new Laminex Distribution Centre is rapidly taking shape. 
Engineering
Victoria Park Alliance >> A Fletcher , Higgins, Beca, Parsons & Brinckerhoff and NZ Transport Agency alliance to design and construct a 2.2km upgrade of SH1 between Wellington Street and the Auckland harbour bridge.
Interiors
AUT WE Stage 2 – School of Art & Design >> The second stage of AUT’s School of Art & Design refurbishment to Levels 5-7 (the two-level first stage refurbishment was completed a year ago).
South Pacific
Leadership Code Commission and Ombudsman’s Office >> Refurbishment of existing and additional offices and amenities.